Project Timeline

Renovation Project Timeline
Dates subject to change
Last updated: March 14, 2016

 Summer-Fall 2014

  • June: Museum & Archives closes
  • July 11: Museum display opens at Merwin House
  • (July 11 – 13, 2014: Annual Used Book Sale)
  • July 13: Library closes on Main Street
  • July 29: Contractor walk-through; bid period
  • August 1: Library reopens at Stockbridge Station
  • August 15: Groundbreaking Ceremony
  • Mid-late August – September: Bids received, reviewed, and contractor accepted
  • October 2014: Construction begins

 

Winter-Spring 2016

  • February: Construction ends
  • March 5: Museum display closes at Merwin House
  • March 31: Temporary Library closes at Stockbridge Station (2 Depot Street)
  • April 30: Grand Re-Opening Celebration